Fuel Berth Staircase La Collette

After submitting a compliant tender Brenwal were appointed as the main contractor to carry out the refurbishment of the platform access staircase at the fuel berth at La Collette. Brenwal also submitted an alternative tender with value engineering due to the specification and the cost of refurbishing the old staircase. It was more feasible to fabricate new galvanised access platforms and staircases. The client took this on board and instructed the contract to proceed with the value engineering applied for the new stair case and platforms.

The contract proceeded with the removal of the old staircase - cut and removed in sections.

The new platforms were part erected on the access road and lifted into place in sections. The fixing plates were enlarged to ensure the original bolts did not interfere with the installation of the fixings.